How Often Does a Crane Need a Thorough Examination?

Twelve months where the crane lifts loads, six where it lifts people. But with cranes the calendar is rarely what catches people out — it is Regulation 9's other trigger, which requires examination after installation and after assembly at each new site, and which a monthly diary reminder will never prompt.

Written and reviewed by Mark Crowley, Director, Integrity Lift Compliance Ltd — 26+ years hands-on lifting equipment engineering — NHS, commercial and industrial estates

What interval applies to a crane?

Twelve months under LOLER Regulation 9 for a crane lifting loads, six where it is used to lift persons — a man-riding application, which is exceptional and carries additional requirements of its own. Lifting accessories used with the crane, including slings, shackles and spreader beams, are on six months regardless, which is a separate programme from the crane itself.

Why does relocation matter more than the date?

Because Regulation 9 requires a thorough examination where safety depends on the installation conditions, after installation and before first use, and again after assembly at each new site. A tower crane or a mast climbing platform erected on a new site needs examining there, on that ground, in that configuration — the certificate from the last site says nothing about this one. This is the trigger most often overlooked.

What does the examiner check on an overhead travelling crane?

The structure — girders, end carriages, welds and bolted connections — plus the long travel and cross travel mechanisms and their rails, the hoist and its brake, the wire rope along its length and at the terminations, the hook and its safety catch, limit switches at every extreme of travel, the overload protection, and the pendant or radio controls including the emergency stop.

Why are hooks measured rather than looked at?

Because a hook deforms gradually under repeated loading, and the throat opens before anything visibly cracks. Examiners measure the throat against its original dimension and look for wear in the saddle, twist across the plane of the hook, and the condition of the safety catch. A hook that has started to open is carrying loads through a changed geometry, and the deterioration accelerates.

What makes wire rope fail an examination?

Broken wires, concentrated in a lay length or at a termination; corrosion, including internal corrosion that shows as a reduction in diameter; deformation such as birdcaging, kinking or core protrusion; and wear on the crown wires from sheave contact. Terminations take disproportionate attention because deterioration concentrates where the rope is held and where it is hardest to inspect.

Does a lift plan still apply if the crane is examined?

Yes, and the two are frequently confused. Regulation 9 covers the equipment's condition. Regulation 8 requires each lifting operation to be properly planned by a competent person, appropriately supervised and carried out safely — the load, the route, the ground, the people beneath. A current examination report demonstrates nothing about how the lift was planned, and prosecutions more often concern the operation than the equipment.

Need a LOLER inspection?

Independent inspection, same-day report with photos

We reply within one business hour, and the inspection is carried out by an engineer with hands-on experience of that kind of plant.

Need this doing rather than just understood?

Independent statutory examination across London, Kent and the South East. We sell no maintenance, repairs or parts, so a defect we record is never a quotation in disguise.

Already overdue? Next working day for an overdue passenger lift in London, same week across Kent and the South East — and what to do in the meantime.